Mouwasat Medical Services Co. announced the continuation of the expansion works at its hospital in Dammam, with construction works having reached 74%.
Trial operations are expected to start in Q4 2020, the company said in a bourse statement on Thursday.
The statement further explained that the previously announced completion date has been delayed due to the COVID-19 restrictions which led to change in construction timeline, in addition to a delay in the supply of construction materials. However, the project’s cost remains the same.
In September 2017, Mouwasat signed a contract worth SAR 150 million with Project Build Co. Ltd. (PBC) to expand the Mouwasat Hospital in Dammam.
The trial operations were expected to start in Q2 2020 for a three-month period, while commercial operations were set to commence after obtaining the required approval from the Ministry of Health.
Argaam Investment Company has updated the Privacy Policy of its services and digital platforms. Know more about our Privacy Policy here.
Argaam uses cookies to personalize content, to provide social media features and analyze traffic, that we might also share with third parties. You consent to our cookies if you use this website
Comments {{getCommentCount()}}
Be the first to comment
رد{{comment.DisplayName}} على {{getCommenterName(comment.ParentThreadID)}}
{{comment.DisplayName}}
{{comment.ElapsedTime}}