Minister of Municipalities and Housing Majid Al-Hogail and Chairman of the Real Estate General Authority (REGA) approved the technical guide for handling delayed and stalled real estate off-plan projects.
According to Umm Al-Qura official gazette, a project is deemed delayed in case it falls behind the schedule.
The delay is defined according to the schedule performance index (SPI).
|
|
Delay |
SPI |
Mild |
From 0.90 to 0.99 |
Medium |
From 0.80 to 0.89 |
Severe |
Less than 0.79 |
Argaam Investment Company has updated the Privacy Policy of its services and digital platforms. Know more about our Privacy Policy here.
Argaam uses cookies to personalize content, to provide social media features and analyze traffic, that we might also share with third parties. You consent to our cookies if you use this website
Comments {{getCommentCount()}}
Be the first to comment
رد{{comment.DisplayName}} على {{getCommenterName(comment.ParentThreadID)}}
{{comment.DisplayName}}
{{comment.ElapsedTime}}