Tabuk Cement announces developments of new mill

26/05/2013 Argaam

Further to Tabuk Cement’s announcements on 25/5/2013 on the latest developments of the new mill project, the company would like to inform stakeholders that the project’s cost announced on 2/7/2011 remain unchanged.

 

The company also states that construction works of the project have taken around two and half months past the schedule announced earlier, due to a belated execution by the contractor.

 

The mill’s test operation is expected to take almost two months, and commercial operation will be announced in due course. 

Comments {{getCommentCount()}}

Be the first to comment

{{Comments.indexOf(comment)+1}}
{{comment.FollowersCount}}
{{comment.CommenterComments}}
loader Train
Sorry: the validity period has ended to comment on this news
Opinions expressed in the comments section do not reflect the views of Argaam. Abusive comments of any kind will be removed. Political or religious commentary will not be tolerated.

Most Read