Further to the announcement posted on Tadawul on 1/1/2014 regarding the postponement of operation of the waste heat recovery (WHR) project, Najran Cement Co. would like to announce that:
1-The electric generators were rented on 31/12/2013 while generators owned by the company had been used.
2-The first connection phase between the first and second lines of the WHR project was finalized in December 2013.
3-The company would like to announce the trial operation of the first phase of the project as of Saturday morning (11/1/2014) for ten days. Commercial operation will be announced on time.
4-The third line of the project will be connected by end of March 2014.
5-The test operation of the second and last stage of the third line connection
process with the WHR project will be in April 2014 for 15 days, and commercial operation will be announced on time, by which time the trial operation of the entire project will be finalized.
Argaam Investment Company has updated the Privacy Policy of its services and digital platforms. Know more about our Privacy Policy here.
Argaam uses cookies to personalize content, to provide social media features and analyze traffic, that we might also share with third parties. You consent to our cookies if you use this website
Comments {{getCommentCount()}}
Be the first to comment
رد{{comment.DisplayName}} على {{getCommenterName(comment.ParentThreadID)}}
{{comment.DisplayName}}
{{comment.ElapsedTime}}