Najran Cement: trial run of WHR project is to last till June

28/04/2014 Argaam

Najran Cement Company expects the trial run for all phases of the Waste Heat Recovery project (WHR) to continue till June 2014.

According to data available by Argaam; the Cement maker started the trial run for phase1 of WHR project on January 11, 2014 and said it is to last till the end of April.

The 2 phases’ project has a production capacity of 12.2 megawatt per hour for phase1 and 27.1 megawatt per hour for phase2 which was expected to commence trial operations in March.

Comments {{getCommentCount()}}

Be the first to comment

loader Train
Sorry: the validity period has ended to comment on this news
Opinions expressed in the comments section do not reflect the views of Argaam. Abusive comments of any kind will be removed. Political or religious commentary will not be tolerated.