City Cement Co. has reached a settlement agreement with Sinoma International Co. on the second production line project, the company said in a bourse filing today.
The Saudi cement producer imposed on Sinoma International a delay interest of 8 percent of the contract’s total value, or a sum of SAR 43 million.
The relevant financial impact will appear on earnings of Q4 2018, the statement added.
City Cement signed in June 2012 a contract with Sinoma International Company to build a second production line with a capacity of 1.9 million tons of clinker per annum at a total cost of SAR 970.63 million.
Argaam Investment Company has updated the Privacy Policy of its services and digital platforms. Know more about our Privacy Policy here.
Argaam uses cookies to personalize content, to provide social media features and analyze traffic, that we might also share with third parties. You consent to our cookies if you use this website
Comments {{getCommentCount()}}
Be the first to comment
رد{{comment.DisplayName}} على {{getCommenterName(comment.ParentThreadID)}}
{{comment.DisplayName}}
{{comment.ElapsedTime}}