City Cement Company said in a statement to Tadawul that the trial run of its second production line starts today with a designed capacity of 5500 tons per day.
The trial run is expected to last for four months the company said without providing any further information regarding anticipated date for commercial production nor the expected financial effect.
According to Argaam; City Cement signed in June 2012 a contract with Sinoma International Company to build a second production line with a capacity of 1.9m tons of clinker per annum at a total cost of SAR 970.63m.